On 8 August 2014 the World Health Organisation
(WHO) categorised the Ebola outbreak in Guinea, Sierra Leone and Liberia as a
Public Health Emergency of International Concern.
multinational corporations with a presence in Africa, and in particular to
those with projects, assets and personnel in those countries affected. The fact
that the WHO has only twice previously described an outbreak in these terms
underlies the severity of its impact, and potential impact, on construction
projects in West Africa.
On the date of the WHO’s announcement, a leading steel producer published
a press release noting that contractors undertaking expansion works at its
mines in Liberia had declared the outbreak a force majeure event and were
moving personnel out of the country. The company noted that it was assessing
the potential impact on the project schedule. This assessment will no doubt
involve a review of its key contracts and the impact of the outbreak on
completion dates and cost. A number of airlines have also cancelled flights to
West Africa, and several mining companies have cut back on nonessential travel
to the region.
companies with interests in West Africa are implementing measures in order to
manage the impact on their businesses in the region and beyond. Our clients are
assessing potential exposure to the consequences of this outbreak and we
highlight below two critical contractual issues that parties must be aware of
in responding to this crisis.
majeure is a principle borrowed from the French civil code, whereby a party
will not be liable for its failure to perform an obligation where this failure
has been caused by the occurrence of exceptional events outside that party’s
control. If there is no force majeure provision in your contract, you will need
to consider other remedies.
potential impact from the Ebola outbreak will be asking themselves two high
level questions: 1) Does this event fit within the definition set out in my
particular contract or contracts?; and 2) Has (or will) the outbreak, as a
matter of fact, impacted (or will it impact) upon my performance or that of my
counterparty under the relevant agreement?
above, the English courts have been reluctant to set out a precise meaning of
the term ‘force majeure’. It follows that where the term is used in a contract;
the ordinary rules of contract interpretation are applicable, such that each
case will be different and turn on the particular words used in the contract.
in which the civil codes prescribe definitions of what is meant by force
majeure. As a result, English law construction/engineering contracts typically
contain an express definition of the phrase to avoid, insofar as it may be
possible, uncertainty and the potential for disputes.
construction projects, it is instructive to consider whether the Ebola outbreak
could be considered a force majeure event within the meaning of the relevant
FIDIC clause, and whether the outbreak would give rise to an entitlement for
additional time or money.
broad definition of a force majeure event as
before entering into the Contract,
avoided or overcome, and
it is a force majeure event (if Clause 19.1 is read in isolation).
categories of examples for force majeure events, including war, rebellion,
riot, and natural catastrophes (such as earthquake, hurricane, typhoon or
volcanic activity).
majeure event (some forms of contract do), though that does not prevent it
being such an event. The critical question to determine whether or not an Ebola
outbreak is a force majeure event, is whether the four criteria set out above
have been satisfied.
be little doubt that the Ebola outbreak is an event which is exceptional;
outside the control of commercial parties to a construction contract; could not
have been avoided/overcome once it arose; and is not substantially attributable
to either party. It would also be difficult to argue that a party to a
construction contract could have provided against the risk of an Ebola outbreak
before entering into the contract (though query whether or not such an outbreak
was foreseeable).
circumstances where the relevant clause includes a requirement that the event
be unforeseeable (the FIDIC example does not). The element of foreseeability is
incorporated in Article 1148 of the French Civil Code, which stipulates that a
force majeure event must be unforeseeable, render performance impossible and be
outside of the control of the party invoking suspension of the relevant
contractual obligation. This is a higher threshold than that in FIDIC and we
have seen agreements where parties have agreed to allocate risk in this way.
Given that, in recent history and in certain parts of West Africa, there have
been Ebola outbreaks, albeit occasional and confined and not necessarily in the
countries currently affected, an Ebola outbreak may fall foul of a force
majeure provision that will not bite where an event is foreseeable.
certainly be entitled to obtain an extension of time in cases where it can
demonstrate delay affecting completion. This would, of course, be subject to
the time bar provisions found in Clause 19.2 relating to notice.
that cost is defined so as to exclude profit in FIDIC RED Book) arising from a
force majeure event is more complex. Clause 19.4 makes a distinction between
different kinds of force majeure events and where they occur. In fact, the
entitlement to cost refers back to the categories of force majeure events
listed in Clause 19.1. For example, an entitlement to additional cost will
accrue in the event that war and/or hostilities in a neighbouring country (or
indeed anywhere) effect the progress of the works. In contrast the balance of
the ‘categories’ of events listed in Clause 19.1 must occur in the country of
the works so as to qualify as a relief event and give rise to an entitlement to
costs.
listed in Clause 19.1, thus creating an uncertainty in the drafting. Is there
an entitlement to an extension of time but no money? Further, if parties are
undertaking projects in adjoining countries, even if they are proximate to the
sites of the Ebola epidemic, does that preclude entitlement to cost?
drafting is unclear on this issue and there is no case-law on epidemics that
would provide useful guidance, the best interpretation of the contract when
read as a whole must be that there is an entitlement to an extension of time,
but not necessarily any cost.
force-majeure-type events may need to consider alternative routes through which
to escape sanction/obtain relief. In such circumstances the English common law
doctrine of frustration may be invoked to provide some level of protection to
the party who would otherwise be in default.
where, for reasons attributable to none of the relevant parties, performance
has become impossible, illegal or would be totally different to what was
contemplated by the parties when the contract was formed.
the effects of the Ebola outbreak could not be mitigated through alternative
methods of performance (for example, procurement of raw materials from
alternate countries/sources unaffected by the outbreak, imposition of stringent
quarantine and medical controls and different techniques and policies to
protect the health and well-being of personnel on site). The English courts
have made it very clear that parties will not be entitled to relief from
performance for frustration merely when performance is rendered more difficult,
time-consuming or expensive.
Consequences of Ebola
contractors undertaking construction projects in West Africa will be determined
by a close reading of the provisions of the relevant contracts (and employing
modern means of interpreting contracts holistically). In many circumstances, we
consider it will be at least arguable that where an outbreak of Ebola has a
demonstrable effect on the progress of a project, it will qualify as a force
majeure event giving rise to an entitlement for time and/or monetary relief,
depending on the express terms of the relevant contract. It may also be the case
that in some civil law jurisdictions parties will be entitled to rely on the
provisions of the civil code in that country to obtain relief.
leader of the Eversheds Africa Law Institute network, and with a presence in 32
African jurisdictions, including Liberia and Sierra Leone, Eversheds is
uniquely placed to assist construction clients across the region.